Quarterly report pursuant to Section 13 or 15(d)

Commitments and Contingencies

v3.19.2
Commitments and Contingencies
3 Months Ended
Jul. 31, 2019
Commitments and Contingencies Disclosure [Abstract]  
Commitments and Contingencies

NOTE 10 — COMMITMENTS AND CONTINGENCIES

 

Mining Leases

 

The Copper King property position consists of two State of Wyoming Metallic and Non-metallic Rocks and Minerals Mining Leases. These leases were assigned to the Company in July 2014 through the acquisition of the Copper King Project. Leases to explore for or use of natural resources are outside the scope of ASU 2016-02 “Leases”.

 

The Company’s rights to the Copper King Project arise under two State of Wyoming mineral leases:

 

1) State of Wyoming Mining Lease No. 0-40828 consisting of 640 acres.

2) State of Wyoming Mining Lease No. 0-40858 consisting of 480 acres.

 

Lease 0-40828 was renewed in February 2013 for a second ten-year term and Lease 0-40858 was renewed for its second ten-year term in February 2014. Each lease requires an annual payment of $2.00 per acre. In connection with the Wyoming Mining Leases, the following production royalties must be paid to the State of Wyoming, although once the project is in operation, the Board of Land Commissioners has the authority to reduce the royalty payable to the State:

 

FOB Mine Value per Ton   Percentage Royalty  
$00.00 to $50.00     5 %
$50.01 to $100.00     7 %
$100.01 to $150.00     9 %
$150.01 and up     10 %

 

The future minimum lease payments under these mining leases are as follows:

 

2020   $ 2,240  
2021     2,240  
2022     2,240  
2023     2,240  
2024     960  
    $ 9,920  

 

The Company may renew each lease for a third ten-year term, which will require one annual payment of $3.00 per acre for the first year and $4.00 per acre for each year thereafter.